• Back to Projects

    Substation Rebuild w/ T-Line By-Pass

    Welty Energy & Infrastructure provided project management services to for the rebuild of an existing radially fed 115/46 kV, two-transformer substation into a four-breaker ring bus configuration. Following the failure of one of the transformers, Welty coordinated the construction activities required for the emergency installation of a mobile transformer. The scope of work included installing a 115kV bypass around the existing station with a radial tap to a mobile transformer, as well as sectionalizing the substation to keep the remaining original transformer online to maintain energization of the 46kV equipment.

    The project also included a new 46kV line tie switch, terminal upgrades at two remote stations, and implementation of anti-islanding protection schemes.

    Project Scope:

    • Demolished a 115kV yard and constructed a new 4-breaker ring bus
    • Installed a new 115kV-46kV transformer, foundation, and oil containment pit
    • Installed new station service transformers
    • Built new control house
    • Installed a 115kV by-pass
    • Installed 46kv line tie switch and structures
    • Reconductored 115kV line exits from station to dead ends
    • Installed a new 115kV breaker and relay panel for line protection
    • Coordinated closely with generation owner and PRC-027 regulations
    • Installed a new synchroscope and two-way anti-islanding protection for generator
    • Installed a new 115kV breaker and relay panel for line protection
    • Installed new two-way anti-islanding protection

    Business Units Involved:

    Welty Energy

    Welty Energy